Control
Costs is the
process of monitoring the status of the project to update the project budget
and managing changes to the cost baseline
Monitor Project status w.r.t. Cost Baseline - Identify the
Variance - Take corrective action to minimize the gap or the associated risk
During Cost Control, It is important to understand the
relation between the two factors below
v
Monitor the expenditure of fundsv Value of the work being accomplished
If we do not understand the relation, then simply tracking
the costs has no value.
Outputs
A. Work Performance
Information: Calculated values of CV SV, CPI, SPI, TCPI and VAC for Work
packages, control accounts
B. Cost Forecasts: EAC,
TCPIC. Change Requests: Approved Change Requests to the cost baseline
D. Project Management
Plan Updates: Changes to cost baseline and cost management plan
E. Organizational
Process Asset updates: Causes of Variances, Corrective action chosen and
the resources.
Tools &
Techniques:
A. Earned Value
Management:
Earned Value Management (EVM) is a methodology that combines scope,
schedule and resource measurements to assess project performance and
progress. EVM integrates Scope base line
+ Cost baseline + Schedule Baseline = to get= Performance Baseline. Thus,
performance baseline helps project management team assess and measure project
performance and progress.
EVM is used
in Project Management to assess
v
Are
we ahead or behind schedulev Are we under or over budget
v How efficiently are we using time & resources?
v What is the remaining and entire project likely to cost
Planned Value (PV) = Authorized Budget Assigned to scheduled
work - Work that "Should
be done"
Earned Value (EV) = Budget Associated with the authorized
work that has been completed – Work that “Has been done”Actual Cost (AC) = Cost incurred till date for the work performed – Cost Spent to complete the work done
Cost Variance (CV) = EV-AC [positive means cost under run, Negative means cost overrun]
Schedule Variance (SV) = EV-PV [Positive means Ahead of the schedule, Negative means behind the schedule]
Cost performance Index (CPI) = EV/AC - Rate at which Cost is
spent = [For every dollar we spent out of our pocket, how much value we are
getting back] - Positive means cost under run - negative means cost overrun.
Schedule performance Index (SPI) = EV/PV - Rate at which
scheduled work is progressing. [i.e. %ge
progress rate at which the scheduled work is being progressed] - Positive means
Ahead of the schedule and Negative means behind the schedule.
Budget At Completion = total Planned Value for the Budgeted
work i.e. Total job
"Supposed to cost" at beginning
Refer the link http://www.krishnamurtybusiness.blogspot.in/
for further details.
B. Forecasting:
EAC (Estimate at Completion) = BAC/CPI (if the future work
is expected to be progressed at the
current run rate) - Total job
"Expected to cost" now
EAC= AC + (BAC-EV) when future work happens at current Rate
EAC= AC+ { [BAC-EC]/CPI * SPI} when project schedule is a
factor that impacts ETC efforts.Variance At Completion = "Will the job" be ahead or under budget - BAC – EAC
C. To-Complete Performance
Index (TCPI):
Rate at which remaining work has to be finished within in
the allocated budget
TCPI = Work Remaining/ Budget Remaining ={ [BAC-EV]/
[BAC-AC])
Gives the run rate at which remaining work to get progressed
to complete the project within the budgeted cost.
TCPI >1 Harder to complete
TCPI = 1 same complexity to complete
TCPI <1 Easier to complete
Source: PMP’s PMBOK
page 224
D. Trend Analysis
- Difference of BAC and EAC - Examines project performance over time to
determine if performance is improving or deteriorating
Earned Value Performance:
All the indices provided in the above chart.
E. Reserve Analysis:
Contingency Reserves are approved for Known and Risks (i.e. Known unknowns)
where risk response strategy is approved by steering committee - It is included
as part of cost baseline -
Cost Baseline = Activity Costs + Contingency reserve costs
Management Reserve - For Unknown Unknowns (i.e. For Unknown
Risks) (eg. Calamity, Earth Quake) - Not included as part of Cost baseline
Project Efforts = Cost Baseline Efforts + Management Reserve
Efforts
Management reserve efforts are taken trough Change control
procedure
F. Project Management
Software: Like Microsoft Project Plan to help plan, organize and manage
resource pools and develop resource estimates- Resource Break down structures,
Resource availability-Resource Rates and various resource calendars to assist
in optimizing resource utilization.
Inputs
Project Management Plan - Project Funding Requirements - Work
Performance Data - Organizational Process Assets (Policies and Procedure
regarding Cost Control, Cost Control Tools and Historical Information, Lessons Learnt,
Monitoring and Reporting Methods to be used)